Lesson Learned - Barriers

A scaffold crew were constructing a system scaffold and were about 22m above the cellar deck of the platform. The first standard was topped out and one of the crew moved on to add the second standard.

During the course of doing this, the second standard fell about 22m, travelling horizontally coming to rest on the cellar deck out with the area which had been barriered.