Testing plant
An important last step in the overhaul process is the trial run of an overhauled idling gearbox on our testing plant.
This testing plant is an area of 60 m2 where our trial run procedure can be run through with 5 gearboxes simultaneously.
It is possible to test up to a power of 187 kW and a rpm of approximately 20,000 rev/min. These high rpms are attained using a "speed-up" gearbox. During this procedure the gearbox is operated for 4 hours, in which the following parameters can be analyzed:
- Temperatures
- Vibrations
- Noise
- Oil viscosity
All testing data is recorded in a test report, which will be sent to the client and filed by us.