Challenge
Major overhaul MAN Turbo 19,4 MW LP and 19,5 MW HP Steam Turbine and Alstom Generator within short lead time.
Solution
- Preparation of procedures with hold and witness points
- Repair of spare LP rotor including re-blading of stage 11 prior to the overhaul
- Disassembly, inspection, repair and assembly of 2-casing Steam Turbine and Generator
- Cold and Hot Commissioning of installation
Benefits
- Execution including extra work within tight lead time
- Full inspection report with recommendations for future maintenance
- Successful commissioning of installation