Advanced Online Desanding at North Sea Installation (2013)

Information

Client

No name

Region

UK North Sea

Industry

Upstream oil and gas

Associated capabilities

Challenge

Stork equipment and personnel were mobilized to complete online desanding onboard a North Sea Installation using the state of the art, Advanced Online Desander (AOD) Skid. The workscopes involved the removal of sand from vessels during the dayshift and deposit removed sand in Drill Cuttings Bins (DCB). The removed sand was washed to under 1% oil on sand during and discharged overboard.

Solution

Stork mobilized a team of eight personnel and Spot, Rigged & Pressure tested equipment to the client’s satisfaction. Removed sand was washed and analyzed prior to being discharged overboard.

Benefits

Successfully desanded 32 tonnes of potentially NORM contaminated sand from the separators using the AOD Skid without the need for well shut in, vessel entry or extended shut down. Client saved significant costs and the sand removal extended the period between shut downs and maintained separator performance. Overall, this project was completed with an overboard discharge average of 0.6%, 6241ppm & zero safety incidents. A high performance standard was achieved through the efficient, safe operation from Stork’s trained and competent crew. Reflective of this is the excellent client feedback received and an average FPAL rating of 8.2 (see service code 3.05.13).

Project details

FPAL rating: M8.7 (see service code 3.05.13)

Date: 2013

Enviromental​: 2 tonnes of sand disposed in line with discharge consent

Safety: Project delivered with no lost time incidents

Division: Environmental & Decontamination

Innovation: Advanced Online Desander Skid